Hi
We are using inspection lots to record supplier results for certain raw materials.
We now need to include our own test results to these inspection lots.
To accomplish this we’re thinking of using the same inspection plan with a 2nd operation.
This will enable us to generate one inspection lot per GR while recording two types of results (i.e. Op1 = Supplier, Op2 = Own).
The inspection lot will always have results from Supplier, but we might only internally test every 10th delivery (GR).
Is it possible to generate the 2nd operation (i.e. Own results) when needed?
Or any other elegant approach/process?
Thanks