Hello,

We have the following scenario : Production is done and then we need about 5 days to control the material. However, the production is running 7/7 24/24, but the lab does run only 3/7 from 8am to 7pm. We cannot use the GR time of MRP2 view, as otherwise, the product is set available Saturday or Sunday for production done Wednesday or Thursday. I tried to use the scheduling function with a work centre opened only on a 3 days calendar in capacity, but this does not work neither, as the time is fixe (4 days) and no calculation is done.

The goal is then to be able to produce at any time, but the get the release of the QM-lot only into the open periods of the lab.

 

Production on Monday           QM-Lot available on Friday

Production on Tuesday          QM-Lot available on next Monday

Production on Wednesday     QM-Lot available on next Monday

Production on Thursday          QM-Lot available on next Wednesday

Production on Friday               QM-Lot available on next Wednesday

Production on Saturday and Sunday     QM-Lot available on next Friday

 

As you can see the delta between production and QM-Lot is not fixed (sometimes 4 , 5 or 6 days).

Any idea how to solve this issue is welcome,

Best regards,

Ju